01
42-line circulatory system.
A 18 basecoats distributed to two booths, 4 clear
coats, 1 solvent and 1 waste line was installed in ½” s.s. tubing. All the Paint modules were
mounted and all lines (air and resins) tied. A main air header was installed with all the
corresponding drops and manifolds.
02
AMU ductwork
A 18 gauge metal sheet duct system of 3 AMU was installed tosuply fresh air to application booths. The 3 AMUS were also mounted








03
Conveyor installation
In this Project we helped a Danish reknown conveyor
manufacturer to install a floor-level conveyor.
04
Overhead conveyor installation
In this Project we helped a Danish reknown
conveyor manufacturer to install an overhead conveyor, from its structure to the carrys.








05
Frame structure for roller curtain.
To be able to install a smaller brand-new roller
curtain it was needed to reinforce Wall and make a new frame for its installation.
06
Installation of sand thermal reclamation system — 5 t/h
Receipt and handling of components, hoisting and assembly of furnace sections, leveling and anchoring, installation of the cooling bed and silo, installation of fans and ductwork, gas and air connections, electrical and control cabinet installation, and start-up testing in coordination with the manufacturer.








07
Preparation & Inspection booths
We assembled a booth for painted parts
inspection and a booth to prepare parts for painting. Its lights, floor platforms and facilities were
also installed afterwards.
08
Intelligent Paint Kitchen (IPK)
Complete mechanical installation of a paint kitchen with Graco equipment: stainless steel tubing, supports, compressed air lines with FRL units, paint tanks, pneumatic agitators and Husky transfer pumps.








09
Stacks installation
Over the years one of the activities that we have done the most is the installation of exhaust stacks, carbón Steel or stainless Steel. So far, 42” it´s been the
bigger diameter.
10
7-Fluid ProDispense System
Mechanical installation of an automated seven-fluid dispensing system, working alongside the project integrator. Scope included high-pressure stainless steel piping, Husky, Fireball and Ram pumps and hose reels with Graco equipment throughout.








11
Paint Touch-Up Stall
Refurbishment and installation of a paint touch-up stall from used equipment. We fabricated the plenum and recirculation ductwork, built a floor-level suction trench and assembled the control panel. In collaboration with EDAG U.S.A. and Panyard Engineering.